Skip to main content
HVAC details, schedules & control sequences
Media Restricted

Object Number219_0230

TitleHVAC details, schedules & control sequences
Date02/21/2014
Additional Firm Gensler
Building/Site(s):
Text Entries
ACCU roof mounting detail -- Refrigerant piping component schematic -- Roof surface mounted piping support (up to 3 in.) -- Pipe hanger support -- Split system air conditioner control sequence -- Duct & pipe penetrations -- Sidewall return grille installation -- Detail of pipe through roof -- Sealing & securing exposed ductliner -- Typical duct installation & support near volume dampers -- Duct hanger support -- Remotely adjustable balancing damper -- Pipe insulation -- Condensate pump schedule -- Split air-conditioning unit schedule -- Diffuser, grille & register schedule -- Minimum duct insulation R-values -- Ductwork pressure class and seal class
Project NumberUIS 2013-0252
Project NameHUIT 8 Story Street renovation - 5th and 6th floor
Consultants Project Number20120749
Sheet NumberH07.00
Access NoteAccess to Property Information Resource Center collections is restricted to approved Harvard University staff, or by permission.
Reproduction NoteNo portion of this object shall be reproduced, released, or distributed by any means without the express written permission of the Harvard University Property Information Resource Center.
ConditionVery Good
DimensionsOverall: 30 × 42 in. (76.2 × 106.7 cm)
MediumBlackline print
Support / MaterialPaper
Extent 1 drawing
Scale NTS
Object Number: 219_0239
Date: 02/21/2014
Project Number: UIS 2013-0252
Sites: 8 Story Street
Project Name: HUIT 8 Story Street renovation - 5th and 6th floor
Object Number: 219_6030
Date: 08/22/2008
Project Number: CADM 2008-0408
Sites: 8 Story Street
Project Name: Islamic Studies Program, 8 Story Street
Object Number: 219_0438
Date: 03/19/2014
Project Number: PIRC 2014-004
Sites: 8 Story Street
Project Name: Renovations to 46 Brattle Street
Object Number: 219_0510
Date: 01/30/2020
Project Number: HRES 2020-0085
Sites: 8 Story Street
Project Name: 8 Story Street chiller and switch gear replacement
Object Number: 219_0516
Date: 01/30/2020
Project Number: HRES 2020-0085
Sites: 8 Story Street
Project Name: 8 Story Street chiller and switch gear replacement
Object Number: 219_0508
Date: 01/30/2020
Project Number: HRES 2020-0085
Sites: 8 Story Street
Project Name: 8 Story Street chiller and switch gear replacement
Object Number: 219_0601
Date: 05/20/2022
Project Number: HRES 2022-0191
Sites: 8 Story Street
Project Name: 8 Story Street HVAC controls
Object Number: PD.2162.001
Date: 2023
Project Number: HRES 2022-0191
Sites: 8 Story Street
Project Name: 8 Story Street HVAC controls
Object Number: PD.2162.002
Date: 2022-2023
Project Number: HRES 2022-0191
Sites: 8 Story Street
Project Name: 8 Story Street HVAC controls
Object Number: PD.2162.003
Date: 2022
Project Number: HRES 2022-0191
Sites: 8 Story Street
Project Name: 8 Story Street HVAC controls
Object Number: PD.2162.005
Date: 2023
Project Number: HRES 2022-0191
Sites: 8 Story Street
Project Name: 8 Story Street HVAC controls
Object Number: PD.2162.006
Date: 06/17/2022
Project Number: HRES 2022-0191
Sites: 8 Story Street
Project Name: 8 Story Street HVAC controls