Skip to main content
Smith Campus Center 10th floor patio window system replacement: CAPS project close-out materials
Image Not Available for Smith Campus Center 10th floor patio window system replacement: CAPS project close-out materials

Object Number2023.05.19.01

TitleSmith Campus Center 10th floor patio window system replacement: CAPS project close-out materials
DescriptionMaterials for this project have been received by the PIRC and are not yet fully cataloged, but may be made available to patrons upon request. Please contact PIRC staff for more information.
Date2023
Building/Site(s):
Project NameSmith Campus Center 10th floor patio window system replacement
Project NumberHRES 2023-0091
Access NoteAccess to Property Information Resource Center collections is restricted to approved Harvard University staff, or by permission.
Reproduction NoteNo portion of this object shall be reproduced, released, or distributed by any means without the express written permission of the Harvard University Property Information Resource Center.
Extent5 drawings
Object Number: 2023.08.03.01
Date: 2022
Project Number: HRES 2022-0212
Sites: Smith Campus Center
Project Name: Smith Campus Center 10th floor restroom project
Object Number: 2024.06.25.01
Date: 2023
Project Number: HRES 2023-0107
Sites: Smith Campus Center, Shops
Project Name: Smith Campus Center retail space HVAC replacement
Object Number: 2017.04.20.01
Date: 10/02/2015
Project Number: HRES 2014-0141
Project Name: Smith Campus Center fire alarm project
Object Number: 2023.07.18.02
Date: 2023
Project Number: HRES 2021-0077
Sites: Smith Campus Center
Project Name: Smith Campus Center 3rd floor bathroom renewal
Object Number: 2021.03.31.02
Date: 2018
Project Number: FGS 2018-0243
Sites: Smith Campus Center
Project Name: Smith Campus Center, Graduate School of Arts and Sciences office renewal
Object Number: 2019.03.27.01
Date: 2018
Project Number: HRES 2014-0055
Sites: Smith Campus Center
Project Name: Richard A. & Susan F. Smith Campus Center - part 1
Object Number: 2024.02.26.01
Date: 2023
Project Number: HRES 2023-0221
Sites: Smith Campus Center, Garage
Project Name: Smith Campus Center Garage renewal
Object Number: 2024.05.17.01
Date: 2023-2024
Project Number: CADM 2023-0227
Sites: Smith Campus Center
Project Name: Smith Campus Center 5th floor renovation Harvard University Planning and Design
Object Number: 2024.05.17.02
Date: 2023-2024
Project Number: HRES 2022-0235
Sites: Smith Campus Center
Project Name: Smith Campus Center 6th floor restroom renewal & tower ventilation
Object Number: 2017.09.25.01
Date: 11/11/2015
Project Number: HRES 2014-0055
Sites: Smith Campus Center
Project Name: Richard A. & Susan F. Smith Campus Center - part 1
Object Number: 2023.07.05.08
Date: 2020
Project Number: HRES 2021-0135
Sites: Cronkhite Center
Project Name: Cronkhite Graduate Center partial roof replacement
Object Number: 2023.07.06.08
Date: 2021
Project Number: SEAS 2021-0027
Sites: Allston Science and Engineering Complex
Project Name: Faculty dry lab fit-out Walsh ATI (replacement Wyss lab)