Object Number568_0419
TitleFinish schedule [2]
Date07/02/2021
Building/Site(s):
Project NumberHLS 2021-0096
Project NameHauser Hall chilled water piping phase 2
Consultants Project Number2018
Sheet NumberA-602
Collection
Architectural & Technical Drawings
Access NoteAccess to Property Information Resource Center collections is restricted to approved Harvard University staff, or by permission.
Reproduction NoteNo portion of this object shall be reproduced, released, or distributed by any means without the express written permission of the Harvard University Property Information Resource Center.
DimensionsOverall: 24 × 36 in. (61 × 91.4 cm)
MediumPDF
Title:
Finish schedule [1]
Object Number: 568_0418
Date: 07/02/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Title:
Electrical schedules [2]
Object Number: 568_0487
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Title:
Room finish schedule
Object Number: 568_0018
Date: 09/15/1992
Project Number: LAW 1991-002
Sites:
Hauser Hall
Project Name: Hauser Hall original construction [New building, Holmes Field]
Title:
Finish schedule
Object Number: 568_0312
Date: 04/01/2012
Project Number: HLS 2012-0064
Sites:
Hauser Hall
Project Name: Hauser Hall basement project
Title:
Level 2 plan
Object Number: 568_0405
Date: 07/02/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0411
Date: 07/02/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Title:
Casework details [2]
Object Number: 568_0417
Date: 07/02/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0493
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Title:
Lighting photometric [2]
Object Number: 568_0496
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0421
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Title:
Mechanical schedules L3
Object Number: 568_0422
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Title:
Mechanical schedules L4
Object Number: 568_0423
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites:
Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2