Skip to main content
2nd floor mechanical room 209, penthouse mechanical room
Media Restricted

Object Number568_0133

Title2nd floor mechanical room 209, penthouse mechanical room
Date02/05/1994
Building/Site(s):
Project NumberLAW 1991-002
Project NameHauser Hall original construction [New building, Holmes Field]
Sheet NumberM-8
Access NoteAccess to Property Information Resource Center collections is restricted to approved Harvard University staff, or by permission.
Reproduction NoteNo portion of this object shall be reproduced, released, or distributed by any means without the express written permission of the Harvard University Property Information Resource Center.
ConditionVery Good
DimensionsOverall: 36 x 48 in. (91.4 x 121.9 cm)
MediumBlackline print
Support / MaterialPaper
Extent 1 drawing
Scale 1/2 in. : 1 ft.
Object Number: 568_0132
Date: 02/05/1994
Project Number: LAW 1991-002
Sites: Hauser Hall
Project Name: Hauser Hall original construction [New building, Holmes Field]
Object Number: 568_0431
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0438
Date: 02/19/2021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0445
Date: 07/02/021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0453
Date: 07/02/021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: UM.N3.0030
Date: 05/28/2010
Project Number: UOS 2008-0528
Sites: Child Hall
Project Name: Northwest Yard utility infrastructure upgrade, phase 2
Object Number: 568_0429
Date: 07/02/2021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0430
Date: 07/02/2021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0437
Date: 07/02/021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0444
Date: 07/02/021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0448
Date: 07/02/021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2
Object Number: 568_0426
Date: 07/02/2021
Project Number: HLS 2021-0096
Sites: Hauser Hall
Project Name: Hauser Hall chilled water piping phase 2