Object NumberUM.N3.0009
TitleUtility profiles [water and sewer]
Date05/28/2010
Building/Site(s):
Text EntriesW-1. Existing 12" water at west of Hauser building to existing 12" water at Harkness courtyard from station W1+00.00 to station W1+94.07 -- W-2. 12"x12"x12" water tee to existing 12" water at Harkness courtyard from station W3+00.00 to station W3+49.96 -- SS-1. 2" sump pump discharge, existing sanitary sewer manhole at north-east of Langdell Hall to steam manhole MH-C1 from station SS1+00.00 to station SS2+50.01
Project NumberUOS 2008-0528
Project NameNorthwest Yard utility infrastructure upgrade, phase 2
Sheet NumberC3.03
Consultants Project Number106072C0
Collection
Maps, Surveys & Infrastructure
NotesUOS 2008-0528 is also known as Package C, UOS 2008-0545 is also known as Package D, UOS 2006-009 is also known as Package A. Package B did not take place.
Access NoteAccess to Property Information Resource Center collections is restricted to approved Harvard University staff, or by permission.
Reproduction NoteNo portion of this object shall be reproduced, released, or distributed by any means without the express written permission of the Harvard University Property Information Resource Center.
ConditionVery Good
DimensionsOverall: 36 × 48 in. (91.4 × 121.9 cm)
MediumBlackline print
Support / MaterialPaper
Object Number: UM.N3.0008
Date: 05/28/2010
Project Number: UOS 2008-0528
Sites:
Child Hall
Project Name: Northwest Yard utility infrastructure upgrade, phase 2
Object Number: UM.N3.0045
Date: 08/27/2010
Project Number: UOS 2008-0545
Sites:
Ames Hall
Project Name: NW Yard Utility Infrastructure upgrade phase 3
Object Number: UM.N3.0046
Date: 08/27/2010
Project Number: UOS 2008-0545
Sites:
Ames Hall
Project Name: NW Yard Utility Infrastructure upgrade phase 3
Title:
Utility profiles [steam]
Object Number: UM.N3.0007
Date: 05/28/2010
Project Number: UOS 2008-0528
Sites:
Child Hall
Project Name: Northwest Yard utility infrastructure upgrade, phase 2
Object Number: UM.N3.0010
Date: 05/28/2010
Project Number: UOS 2008-0528
Sites:
Child Hall
Project Name: Northwest Yard utility infrastructure upgrade, phase 2
Object Number: UM.N3.0047
Date: 08/27/2010
Project Number: UOS 2008-0545
Sites:
Ames Hall
Project Name: NW Yard Utility Infrastructure upgrade phase 3
Object Number: UM.N3.0048
Date: 08/27/2010
Project Number: UOS 2008-0545
Sites:
Ames Hall
Project Name: NW Yard Utility Infrastructure upgrade phase 3
Object Number: US.N3.0010
Date: 08/28/2008
Project Number: UOS 2006-009
Sites:
Child Hall
Project Name: Northwest Yard utility infrastructure upgrade, phase 1
Title:
Utility site plan
Object Number: UM.N3.0005
Date: 05/28/2010
Project Number: UOS 2008-0528
Sites:
Child Hall
Project Name: Northwest Yard utility infrastructure upgrade, phase 2
Title:
Utility stationing plan
Object Number: UM.N3.0006
Date: 05/28/2010
Project Number: UOS 2008-0528
Sites:
Child Hall
Project Name: Northwest Yard utility infrastructure upgrade, phase 2
Title:
Overall utility site plan
Object Number: UM.N3.0040
Date: 08/27/2010
Project Number: UOS 2008-0545
Sites:
Ames Hall
Project Name: NW Yard Utility Infrastructure upgrade phase 3
Title:
Utility site plan
Object Number: UM.N3.0041
Date: 08/27/2010
Project Number: UOS 2008-0545
Sites:
Child Hall
Project Name: NW Yard Utility Infrastructure upgrade phase 3